induwara.lkinduwara.lk
induwara.lkSri Lanka · Construction

Sri Lanka House Construction Material Calculator

Estimate cement, sand, metal, bricks, blocks, TMT steel and roof material for a Sri Lankan house in seconds. Per-unit consumption rates from CIDA Specifications and ICTAD's Method of Measurement — enough to sanity-check a contractor's BOQ before paying the advance.

By Induwara AshinsanaUpdated May 16, 2026
House material estimateCIDA / ICTAD residential rates
CIDA verified · 2026
sqft

Total built-up area across all storeys. ≈ 92.9 m².

Footprint ≈ 92.9 m² per floor.

Quick presets

Used for all external walls; v1 uses one thickness throughout.

Drives the slab / rafter / sheet line items and steel demand.

Typical residential: 3 ft on firm soil, 5 ft on filled land.

ICTAD residential default is 7.5 %.

Cement (50 kg bags)
110
27 foundation · 32 walls
Bricks
11,508
Wall area 82.35 m²
River sand
388 ft³
Metal: 295 ft³
TMT steel
659 kg
RCC volume 8.82 m³
Outside the published rule-of-thumb band
Detailed estimate: 110 bags. Published band: 400550 bags. The band uses 0.40–0.55 bags/sqft for one storey, 0.50–0.65 for two, 0.60–0.75 for three — CIDA contractor briefing notes for BOQ verification.

BOQ summary

Line itemQuantitySource / clause
Cement (50 kg bags)
110 bagsCIDA Specifications for Building Works (SCA/8) §3–5 (masonry, plaster, concrete)
River sand (fine aggregate)
388.5 ft³ICTAD Method of Measurement of Building Works (DEV/MMBW) Table 3-A
Metal (3/4″ coarse aggregate)
295.3 ft³CIDA Specifications for Building Works (SCA/8) §5 (Concrete Works)
Bricks (9-inch brick (225 mm))
11,508 nosSLS 855 burnt-clay brick (222×104×64 mm)
Reinforcement steel (TMT rebar)
659 kgICTAD Method of Measurement of Building Works (DEV/MMBW) — 90 kg/m³ residential weighted average
Calicut clay roof tiles
1,608 nosCIDA RCS 4.2 — 14 tiles/m² with laps
Roof timber (rafters + battens)
5.2 CIDA RCS 4.2
Indicative material cost (Western Province retail)
Rs 1,086,346range Rs 923,394Rs 1,249,298

Materials only. Excludes labour, transport, scaffolding, fittings, plumbing, electrical, and finishes. Verify each rate with your nearest hardware supplier before signing a contract.

Estimate only — your contractor's site survey may add earthworks, retaining walls and finishes outside this tool's scope.

How it works

The calculator walks the same six-stage take-off a Sri Lankan quantity surveyor builds when preparing a BOQ for a residential house: geometry → masonry → plaster → concrete → reinforcement → finishes. Every per-square-metre coefficient below traces back to a published CIDA or ICTAD clause, and each line in the BOQ summary cites the source it came from.

1. Geometry from floor area

Floor area in square feet is converted to square metres (1 m² = 10.764 sqft). A 1:1.4 rectangular footprint is assumed — this is the ICTAD-residential central value for single-family Sri Lankan houses — and the external perimeter is derived as P = 2 × (1 + 1.4) × √(footprint / 1.4). Wall area is the perimeter × storey height (2.7 m) × number of storeys, with a 22 % deduction for doors and windows. From the second storey onwards the tool adds 18 % to the perimeter to cover interior partitions and stair-well walls.

2. Masonry — bricks and mortar

A 9-inch brick wall in 1:5 cement mortar uses 130 bricks, 0.36 bags of cement and 2 ft³ of sand per m² of finished wall (ICTAD MMBW Table 3-A). A 4.5-inch partition is half of those numbers. Six-inch hollow cement blocks (400 × 200 × 150 mm, SLS 1397) come in at 12.5 blocks per m² with a leaner 1:6 mortar.

3. Plaster — both faces

12 mm 1:5 plaster on a single face consumes 0.18 bags of cement and 0.36 ft³ of sand per m² of wall (CIDA SCA/8 §4). The calculator doubles those numbers to 0.36 bags + 0.72 ft³ per m² when you tick “plaster both faces”. Internal-only plastering (one face) is rare in Sri Lankan residential practice because exposed brick weathers poorly in the monsoon, so this is on by default.

4. Concrete — foundation and above-grade RCC

Foundation volume = perimeter × trench width × depth × 1.5 (the 1.5 multiplier accounts for over-excavation and back-fill). Of that trench volume, 25 % is 1:3:6 reinforced concrete footing — 4.2 bags, 16.3 ft³ sand and 32.6 ft³ metal per m³ — and 75 % is rubble masonry packing. Trench width steps up with storey count: 0.45 m for a bungalow, 0.60 m for two storeys, 0.75 m for three.

Above-grade structural RCC (1:2:4) covers lintels, ring beams, columns and the slab where applicable. The volume per m² of total floor area is 0.03 m³/m² for a tile roof (just lintels, columns and the ground beam), 0.072 m³/m² for a full RCC slab roof (slab + supporting beams + columns), and 0.022 m³/m² for a lighter asbestos sheet roof. A 1:2:4 cubic metre needs 6.4 bags + 14 ft³ sand + 28 ft³ metal.

5. Reinforcement steel

ICTAD's residential benchmark is 60 kg/m³ in the foundation footing and 90 kg/m³blended for the above-grade RCC (a weighted average of 100 kg/m³ for beams, 110 kg/m³ for columns and 80 kg/m³ for slabs, which is what a typical residential design comes out to). The mix of TMT bar diameters is set by the structural engineer's drawings, so this tool reports a single kilogram total rather than guessing a Y10 / Y12 / Y16 split.

6. Roof finish

A calicut clay tile roof needs 14 tiles per m² of roof area and 0.045 m³ of timber per m² for rafters, battens and the ridge piece (CIDA RCS 4.2). The roof itself is 15 % larger than the floor footprint because of pitch and overhang, so a 1,000 sqft house has about 107 m² of roof and ≈ 1,500 tiles before wastage. An asbestos sheet roof uses 0.95 sheets per m² of roof area; an RCC slab roof is already captured in the above-grade concrete line.

Cross-check against the published rule-of-thumb

The detailed estimate is reconciled against the CIDA contractor briefing band of 0.40–0.55 bags per sqft for single-storey houses, 0.50–0.65 for two-storey and 0.60–0.75 for three-storey. When the two methods agree (which they should for any reasonable input), the calculator shows a green “cross-checked” tick. When they disagree, the result is flagged as outside the published band so you can investigate the geometry assumptions before trusting the number.

What the calculator does not include

Labour, transport, scaffolding, plumbing, electrical, painting, tiling, joinery, fittings, boundary walls, gates, parking, driveways, septic tanks, water tanks, statutory approvals, professional fees and the cost of land. The scope is the structural shell — foundation, walls, plaster, RCC, roof finish — because those are the lines a contractor's BOQ inflates first and the ones you can sanity-check with published per-unit rates. For municipal approval fees use the building approval fee calculator.

Worked examples

Three scenarios that map to common Sri Lankan residential builds. Each was computed by the calculator itself, so the numbers on this page always match the output you'll see when you enter the same inputs above.

Example 1 — 1,000 sqft single-storey, 9-inch brick, tile roof

Most common SL village/suburban build. Plaster on both sides, 3 ft foundation, 7.5 % wastage.

  1. Floor area: 1,000 sqft = 92.9 m²; footprint 92.9 m²
  2. External perimeter (1:1.4 aspect): 39.1 m
  3. Net wall area after 22 % opening deduction: 82.35 m²
  4. Walls (9-inch brick): 11,508 bricks, 32 bags cement
  5. Plaster (both faces): 32 bags cement
  6. Foundation (1:3:6): 6 m³ concrete, 27 bags cement
  7. Above-grade RCC (1:2:4 lintels + ground beam): 2.8 m³, 19 bags cement
  8. Total cement: 110 bags
  9. Roof: 1,608 calicut tiles, 5.2 m³ timber
  10. Steel: 659 kg TMT rebar (foundation + RCC)

Example 2 — 1,800 sqft two-storey, 9-inch brick, RCC slab roof

Two-storey detached house, modern construction. Plaster both sides, 3 ft foundation, 7.5 % wastage.

  1. Floor area (total): 1,800 sqft = 167.22 m²; footprint per storey 83.61 m²
  2. Perimeter (with +18 % interior partition factor for upper floor): wall area 184.37 m²
  3. Walls (9-inch brick all-round): 25,765 bricks, 71 bags cement
  4. Plaster (both faces): 71 bags cement
  5. Foundation (deeper trench, 0.60 m wide): 7.6 m³, 34 bags cement
  6. Above-grade RCC (slab + beams + columns, 0.072 m³/m²): 12 m³, 83 bags cement
  7. Total cement: 260 bags
  8. Steel: 1,657 kg TMT (foundation 60 kg/m³ + RCC 90 kg/m³)
  9. Sand: 854 ft³ · Metal: 630 ft³

Example 3 — Edge case: small 600 sqft, 6-inch block, asbestos roof

Small starter house or annex. No plaster, 2 ft foundation, 5 % wastage. Tests the asbestos + block + no-plaster branches.

  1. Floor area: 600 sqft = 55.74 m²; footprint 55.74 m²
  2. Net wall area: 63.79 m²
  3. Walls (6-inch block): 837 blocks, 7 bags cement
  4. Plaster: 0 bags (plaster turned off — finish with cement-sand skim or paint directly on blockwork)
  5. Foundation (1:3:6, 2 ft deep): 3.1 m³, 14 bags cement
  6. Above-grade RCC (asbestos roof rate, 0.022 m³/m²): 1.2 m³, 8 bags cement
  7. Total cement: 29 bags
  8. Asbestos sheets: 64 (8′ × 3′ corrugated)
  9. Steel: 312 kg TMT

Frequently asked questions

Sources & references

Related tools

Rate this tool
Be the first to rate

Comments & feedback

Spotted a bug or want an improvement? Tell us — our team reviews every comment, and good ideas get built. Comments are public and anonymous.

Found a bug, edge case, or want to suggest an improvement?

Email me at [email protected] — most fixes ship within 24 hours.