CIDA Grading Sri Lanka — Grade & Registration Fee Calculator

Every government bid notice in Sri Lanka names a CIDA grade. Enter a contract value and this tool returns the grade that can bid for it, the band CIDA prints, and the itemised registration cost with VAT — from the Authority's own tables, limits effective 01.04.2025. Or pick your grade to see its ceiling.

By Induwara AshinsanaUpdated Sep 27, 2026
Which CIDA grade, and what does it cost?
CIDA limits · effective 01.04.2025

Specialities on this ladder: Building Construction · Highway Construction · Bridge Construction · Water Supply and Sewerage · Irrigation and Drainage Canals · Dredging and Reclamation · Storm Water Disposal and Land Drainage · Maritime Construction · Heavy Construction (areas to be specified). They all share the same financial limits and the same fees.

In Rs million, the way bid notices print it — 250 means Rs 250,000,000. Up to 100,000.

CIDA charges per year; a registration runs 3 years.

Changing your business name, your company status, or filling up the Record Book carries its own fee, priced in two columns by grade.

VAT
Try a case
A contract of Rs 250 million needs CIDA grade C4

Main (C) · financial limit 300 ≥ X > 100 (Rs million) · over Rs 100 Mn, up to Rs 300 Mn

Total payable (incl. VAT)
Rs 143,960.00
3 years of registration + processing
Application processing
Rs 2,000
One-off, excluding VAT
Registration per year
Rs 40,000
Published rate, excluding VAT
Contract ceiling
Rs 300 Mn
Band: 300 ≥ X > 100

Fee breakdown

ItemNetVATPayable
Application processing feeOne-off, on submission of the C4 applicationRs 2,000Rs 360.00Rs 2,360.00
Registration fee × 3 yearsRs 40,000 per year × 3Rs 120,000Rs 21,600.00Rs 141,600.00
Total including VATRs 122,000Rs 21,960.00Rs 143,960.00

Headroom inside C4

Rs 50 Mn

Left between this contract and the C4 ceiling of Rs 300 million.

The grade above

C3Rs 600 Mn

Rs 184,080.00 for the same 3-year period — Rs 40,120.00 more than C4. Fees are only part of it: CIDA still has to assess your financial capacity, staff, plant and experience.

Worth knowing

  • The 3-year figure is 3 × the published annual rate. CIDA publishes a fee per year and a validity of 3 years, but does not say on that page whether the 3 years are invoiced upfront — confirm the payment schedule with CIDA's Development Division.
  • CIDA quotes 2 weeks to process a C4 application, and says processing can be expedited for an extra fee that depends on the grade. That surcharge is not published, so it is not in the total above.

Main Contractor — Building & Civil Engineering (C) — grades and financial limits

GradeFinancial limit (X) Rs MnProcessing feeRegistration / yearRecord Book column
CS2X > 6000Rs 12,000Rs 700,000C4 & above, GP-B1, GP-P, EM1, SP1
CS16000 ≥ X > 3000Rs 12,000Rs 420,000C4 & above, GP-B1, GP-P, EM1, SP1
C13000 ≥ X > 1200Rs 6,000Rs 200,000C4 & above, GP-B1, GP-P, EM1, SP1
C21200 ≥ X > 600Rs 6,000Rs 75,000C4 & above, GP-B1, GP-P, EM1, SP1
C3600 ≥ X > 300Rs 6,000Rs 50,000C4 & above, GP-B1, GP-P, EM1, SP1
C4300 ≥ X > 100Rs 2,000Rs 40,000C4 & above, GP-B1, GP-P, EM1, SP1
C5100 ≥ X > 50Rs 2,000Rs 28,000Up to C5 / EM2 / SP2 / GP-B2
C650 ≥ X > 20Rs 2,000Rs 22,000Up to C5 / EM2 / SP2 / GP-B2
C720 ≥ X > 10Rs 500Rs 15,000Up to C5 / EM2 / SP2 / GP-B2
C810 ≥ X > 04Rs 500Rs 8,000Up to C5 / EM2 / SP2 / GP-B2
C904 ≥ XRs 500Rs 6,000Up to C5 / EM2 / SP2 / GP-B2

All fees exclusive of VAT, as CIDA prints them. Financial limits effective 01.04.2025. Each band's upper bound is inclusive and its lower bound exclusive, so a contract sitting exactly on a boundary takes the lower grade.

Sources cited:every grade, band and rupee figure above is transcribed from CIDA's own Registration and Grading Scheme page, whose limits are marked effective 01.04.2025, and the processing times from its How to apply page. VAT is the statutory 18%. Full citations and the method are below the calculator.

How it works

CIDA registration is a screening process, not a licence you buy. The Authority grades a contractor on financial capability, technical staff, plant and machinery, and experience in the relevant field, and the grade it awards carries a financial limit — the value of the largest single contract that contractor may take on. Because the Treasury requires procuring entities to specify a grade, that limit is what decides whether you can bid at all. The calculation above has four steps, and none of them estimates anything.

  1. Pick the ladder. CIDA publishes five, not four: Main (C), E&M (EM), Specialised (SP-C), Piling pre-cast, Piling bored. Piling is printed as two separate ladders — pre-cast and bored cast in-situ — with different bands and different fees, so this tool keeps them apart. Within the Main ladder all nine specialities — Building, Highway, Bridge, Water Supply and Sewerage, and the rest — share one set of limits, so the speciality changes the field of work, never the fee.
  2. Match the value to a band. CIDA prints each band as an inequality — C4 is 300 ≥ X > 100 — with the upper bound closed and the lower bound open. So the rule is: the matching grade is the lowest grade whose upper limit is at or above the contract value, and a value sitting exactly on a boundary resolves downwards. Rs 600 million is C3, not C2. Every boundary is a round number a reader is likely to type, so each one is pinned by an executable check. Pre-cast piling is the one exception: its band is printed X ≥ 100, with an inclusive lower bound and nothing published below it, and the tool says so instead of inventing a grade.
  3. Add the fees. Each grade carries a one-off application processing fee and a registration fee per year, both published exclusive of VAT. The total is processing + (annual × years) + record book, then × 1.18. VAT is the statutory 18% rate, read from the same module behind the VAT calculator. Record Book changes — a name change, a change of company status, a book whose pages have filled up — are a separate published fee, charged in two columns: one for grades up to C5 / EM2 / SP2 / GP-B2, the other for C4 and above, GP-B1, GP-P, EM1 and SP1.
  4. Report the headroom. For a finite ceiling the tool subtracts the contract value from it, so you can see how much of the band a job uses up. For CS2, EM1, SP1, GP-B1 and GP-P, which have no published upper limit, it says so rather than printing a number.

Two things this tool will not do. It does not predict whether CIDA will award you a grade — those point-system thresholds sit in the priced Guidelines document CIDA/ID/10 and are not published. And it does not price expedited processing: CIDA says the surcharge exists and varies by grade, without publishing the amounts.

Both the band table and the fee arithmetic are checked against a second implementation written straight from the printed inequality strings, across every band edge of every ladder and each side of it. 40/40 checks pass, including the worked examples below.

Worked examples

Rs 250 million water-supply contract, Main ladder, full 3-year cycle

  1. 250 falls in the C4 band, 300 ≥ X > 100 → C4
  2. Application processing fee 2,000
  3. Registration Rs 40,000 per year × 3 120,000
  4. Subtotal (as CIDA publishes it, net of VAT) 122,000
  5. VAT 122,000 × 0.18 21,960
  6. TOTAL Rs 143,960
  7. Headroom: 300 − 250 = Rs 50 million left inside C4

EM3 contractor offered a Rs 60 million MVAC contract — the upgrade case

  1. EM3's band is 50 ≥ X > 20, so its ceiling is Rs 50 Mn → EM3 cannot bid
  2. 60 falls in 100 ≥ X > 50 → EM2 is required
  3. EM2 application processing fee 4,500
  4. EM2 registration Rs 40,000 per year × 3 120,000
  5. Subtotal 124,500
  6. VAT 124,500 × 0.18 22,410
  7. TOTAL for the cycle Rs 146,910

C9 jobbing builder renewing for one year — the smallest bill on the ladder

  1. C9's band is 04 ≥ X: contracts up to Rs 4 million
  2. Application processing fee 500
  3. Registration Rs 6,000 per year × 1 6,000
  4. Subtotal 6,500
  5. VAT 6,500 × 0.18 1,170
  6. TOTAL Rs 7,670

A contract of exactly Rs 600 million — the boundary case

  1. C3 is printed 600 ≥ X > 300 · C2 is printed 1200 ≥ X > 600
  2. 600 satisfies 600 ≥ X, and does NOT satisfy X > 600
  3. So Rs 600 million is C3, not C2 → C3
  4. C3: processing 6,000 + registration 50,000 × 3 = 156,000 net
  5. VAT 156,000 × 0.18 = 28,080 → TOTAL Rs 184,080
  6. Headroom: 600 − 600 = Rs 0 — this contract sits on the C3 ceiling

CIDA registration cost by grade — full 3-year cycle

Main Contractor ladder, application processing fee plus 3 years of registration fee, VAT at 18% included. Limits effective 01.04.2025.

GradeContract limit (Rs Mn)Per year3-year cycle, incl. VAT
CS2X > 6000Rs 700,000Rs 2,492,160
CS16000 ≥ X > 3000Rs 420,000Rs 1,500,960
C13000 ≥ X > 1200Rs 200,000Rs 715,080
C21200 ≥ X > 600Rs 75,000Rs 272,580
C3600 ≥ X > 300Rs 50,000Rs 184,080
C4300 ≥ X > 100Rs 40,000Rs 143,960
C5100 ≥ X > 50Rs 28,000Rs 101,480
C650 ≥ X > 20Rs 22,000Rs 80,240
C720 ≥ X > 10Rs 15,000Rs 53,690
C810 ≥ X > 04Rs 8,000Rs 28,910
C904 ≥ XRs 6,000Rs 21,830

CIDA publishes the fee per year and a validity of 3 years, without stating on that page whether the cycle is invoiced upfront. Treat the right-hand column as the 3-year cost at the published annual rate and confirm the payment schedule with CIDA's Development Division.

Record Book change fees, as CIDA prints them

Every fee here is exclusive of VAT. The two columns are CIDA's own split by grade.

No.StatusUp to C5 / EM2 / SP2 / GP-B2C4 & above, GP-B1, GP-P, EM1, SP1
01 (a)Individual ownership converting to a partnershipRs 2,500Rs 6,000
01 (b)Adding partner / partners to an existing partnershipRs 2,500Rs 6,000
01 (c)Removing partners from an existing partnershipRs 5,000Rs 10,000
01 (d)Individual ownership or partnership converting to a limited liability companyRs 15,000Rs 25,000
01 (e) IChange of name — individual businessRs 2,500Rs 6,000
01 (e) IIChange of name — partnershipRs 4,000Rs 7,000
01 (e) IIIChange of name — (Pvt) LtdRs 12,000Rs 27,500
02Loss of Record Book (police entry + affidavit required)1st duplicate Rs 30,000 · 2nd issue Rs 75,000 · 3rd issue Rs 125,0001st issue Rs 75,000 · Rs 125,000
03Change of staff——
04New Record Book (pages become full)Rs 1,500Rs 1,500

All copies of documents submitted are to be certified by a Notary Public or a lawyer.The calculator above prices the name, company-status and new-book rows. It leaves out “Loss of Record Book”, because CIDA's grid lists three issue numbers in the left column and only two in the right, so a first-issue duplicate cannot be priced in the right-hand column without inventing the missing cell.

What else the application involves

  • Registration runs for 3 years from the date it is granted, then has to be renewed.
  • CIDA quotes 2 weeks to process an application for C6 and above, and 7 working days for the grades below it.
  • Processing can be expedited for an extra fee that CIDA says depends on the grade. The amounts are not published, and a copy of the tender notice has to be submitted with the request.
  • The applicant company must be registered in Sri Lanka — with the Registrar of Companies or a Provincial Secretary — and at least 51% owned by Sri Lankan nationals.
  • Grading is a capability assessment, not a purchase. CIDA scores financial capacity, technical staff, plant and experience against its Guidelines for Grading of Construction Contractors (CIDA/ID/10), which is sold at the CIDA Information Centre and not published online.
  • Forms and guidelines are bought at the Information Centre on the ground floor of CIDA head office, Savsiripaya, 123 Wijerama Mawatha, Colombo 07, and the completed application is handed back there.
  • Minimum 51% Sri Lankan ownership applies to this scheme. Foreign construction contractors register under a separate CIDA scheme with its own fee table, which this page does not cover.
  • Once you know the grade, the money questions that follow are the build cost and the council's permit. The house construction cost calculator and the building approval fee calculator handle those.

Frequently asked questions

Sources & references

Every grade, band and rupee figure on this page was read from those CIDA pages on 2026-09-27. The grading page carries its own note, “Financial Limits (Effective from 01.04.2025)”. The schedule changes only when CIDA reissues it, so this page is re-checked every six months and after any CIDA fee revision.

Related tools

Comments & feedback

Spotted a bug or want an improvement? Tell us — our team reviews every comment, and good ideas get built. Comments are public and anonymous.

Paid a different amount at the CIDA Information Centre, or had a grade read differently at a bid opening? That is the one thing I cannot check from here.

Email me at [email protected] — most fixes ship within 24 hours.