Concrete material estimatenominal mix
Dry-volume method · ×1.54
Mix ratio (cement : sand : metal)

Grade 15 (M15) General house slabs, floors, non-structural work

Extra to order for spillage and over-excavation. 5% is typical.

Cement
24bags (50 kg)
1,177 kg total
Sand
0.58cube
57.8 ft³ · 1.64 m³
Metal (aggregate)
1.16cube
115.5 ft³ · 3.27 m³
Water
589litres
at chosen water-cement ratio

Reference

Wet volume
3.54 m³
125 ft³
Dry volume (×1.54)
5.72 m³
after wastage
Grade / cross-check
Grade 15 (M15)
6.65 bags/m³

Material split (dry volume)

Cement: 0.82Sand: 1.64Metal: 3.27

Sources: CIDA Method of Measurement (SL site units), SLS 107 (50 kg bag, cement density 1440 kg/m³) and IS 456:2000 Table 9 (nominal mixes). 1 cube = 100 ft³. Estimates for ordering only — confirm with your engineer for structural work.

How it works

The calculator uses the nominal-mix dry-volume (absolute-volume) method — the same estimating convention used in CIDA/ICTAD rate build-ups and the IS 456:2000 nominal mixes widely followed on Sri Lankan sites. It converts your pour into a dry quantity of each material, then reports cement in 50 kg bags and sand and metal in the volumetric units hardware stores sell in.

  1. Wet volume. From dimensions, all measurements are converted to metres and multiplied (V = L × W × T). By volume, cubes (×2.832 m³), cubic feet (÷35.3147) or m³ are used directly.
  2. Wastage. The wet volume is scaled by (1 + wastage/100) so you order enough for spillage and over-excavation.
  3. Dry volume. Multiply by 1.54. Loose dry materials lose about 35% of their bulk once mixed with water, so 1/(1−0.35) ≈ 1.54 gives the dry quantity needed for that wet volume.
  4. Ratio split. For a mix a:b:c with sum S = a+b+c, the dry volume is split cement = D×a/S, sand = D×b/S, metal = D×c/S.
  5. Cement mass & bags. Cement volume × 1440 kg/m³ (SLS bulk density) gives the mass; dividing by 50 kg (SLS 107 bag) and rounding up gives whole bags.
  6. Sand & metal. Sold by volume in Sri Lanka, so each is shown in m³, then ft³ (×35.3147), then cubes (÷100 ft³).
  7. Water. Litres = water-cement ratio × cement mass in kg (1 litre of water ≈ 1 kg).

As a credibility cross-check, the per-cubic-metre cement figure the tool reports reproduces the published nominal-mix values exactly: 1:2:4 → 6.34 bags/m³ and 1:1.5:3 → 8.06 bags/m³. If your figure lands within rounding of these, the estimate is sound. Nominal mixes cover work up to about Grade 25 — designed high-grade concrete (M30+) needs an IS 10262 mix design and is out of scope here.

Worked examples

House slab — 1:2:4

20 ft × 15 ft × 5 in, 5% wastage

  1. Wet V = 6.096 × 4.572 × 0.127 = 3.540 m³ (= 125 ft³)
  2. After 5% wastage: 3.540 × 1.05 = 3.717 m³
  3. Dry D = 3.717 × 1.54 = 5.724 m³; ratio sum = 7
  4. Cement = 5.724 ÷ 7 = 0.818 m³ → 1177 kg → 23.55 → 24 bags
  5. Sand = 5.724 × 2/7 = 1.635 m³ = 57.8 ft³ = 0.58 cube
  6. Metal = 5.724 × 4/7 = 3.271 m³ = 115.5 ft³ = 1.16 cube
  7. Water @ 0.50 = 0.50 × 1177 = 589 litres

1 m³ footing — 1:1.5:3

By volume, no wastage (M20 cross-check)

  1. Dry D = 1.00 × 1.54 = 1.54 m³; ratio sum = 5.5
  2. Cement = 1.54 ÷ 5.5 = 0.28 m³ → 403.2 kg → 8.06 → 9 bags
  3. Raw 8.06 bags/m³ matches the published M20 ≈ 8 bags/m³ figure ✓
  4. Sand = 1.54 × 1.5/5.5 = 0.42 m³ = 14.83 ft³ = 0.148 cube
  5. Metal = 1.54 × 3/5.5 = 0.84 m³ = 29.66 ft³ = 0.297 cube
  6. Water @ 0.50 = 0.50 × 403.2 = 202 litres

Column footing — 1:1:2 (Grade 25)

4 ft × 4 ft × 1.5 ft, 5% wastage

  1. Wet V = 1.219 × 1.219 × 0.457 = 0.679 m³ (= 24 ft³)
  2. After 5% wastage: 0.679 × 1.05 = 0.713 m³
  3. Dry D = 0.713 × 1.54 = 1.098 m³; ratio sum = 4
  4. Cement = 1.098 ÷ 4 = 0.2747 m³ → 395.6 kg → 7.9 → 8 bags
  5. Sand = 1.098 × 1/4 = 0.274 m³ = 9.69 ft³ = 0.097 cube
  6. Metal = 1.098 × 2/4 = 0.549 m³ = 19.4 ft³ = 0.194 cube

Frequently asked questions

Sources & references

Coefficients and the dry-volume factor on this page were last cross-checked against the sources above on 2026-07-11. Cement bag mass and density follow SLS 107; site units (cube = 100 ft³) follow standard Sri Lankan practice. Estimates are for material ordering — confirm structural mixes with your engineer.

Related tools

Rate this tool
Be the first to rate

Comments & feedback

Spotted a bug or want an improvement? Tell us — our team reviews every comment, and good ideas get built. Comments are public and anonymous.

Found a bug, edge case, or want to suggest an improvement?

Email me at [email protected] — most fixes ship within 24 hours.