How it works
The calculator uses the nominal-mix dry-volume (absolute-volume) method — the same estimating convention used in CIDA/ICTAD rate build-ups and the IS 456:2000 nominal mixes widely followed on Sri Lankan sites. It converts your pour into a dry quantity of each material, then reports cement in 50 kg bags and sand and metal in the volumetric units hardware stores sell in.
- Wet volume. From dimensions, all measurements are converted to metres and multiplied (V = L × W × T). By volume, cubes (×2.832 m³), cubic feet (÷35.3147) or m³ are used directly.
- Wastage. The wet volume is scaled by (1 + wastage/100) so you order enough for spillage and over-excavation.
- Dry volume. Multiply by 1.54. Loose dry materials lose about 35% of their bulk once mixed with water, so 1/(1−0.35) ≈ 1.54 gives the dry quantity needed for that wet volume.
- Ratio split. For a mix a:b:c with sum S = a+b+c, the dry volume is split cement = D×a/S, sand = D×b/S, metal = D×c/S.
- Cement mass & bags. Cement volume × 1440 kg/m³ (SLS bulk density) gives the mass; dividing by 50 kg (SLS 107 bag) and rounding up gives whole bags.
- Sand & metal. Sold by volume in Sri Lanka, so each is shown in m³, then ft³ (×35.3147), then cubes (÷100 ft³).
- Water. Litres = water-cement ratio × cement mass in kg (1 litre of water ≈ 1 kg).
As a credibility cross-check, the per-cubic-metre cement figure the tool reports reproduces the published nominal-mix values exactly: 1:2:4 → 6.34 bags/m³ and 1:1.5:3 → 8.06 bags/m³. If your figure lands within rounding of these, the estimate is sound. Nominal mixes cover work up to about Grade 25 — designed high-grade concrete (M30+) needs an IS 10262 mix design and is out of scope here.
Worked examples
Frequently asked questions
Sources & references
- CIDA — Construction Industry Development Authority of Sri Lanka (Method of Measurement, rate build-ups)
- SLSI — SLS 107 Ordinary Portland Cement (50 kg bag, cement density 1440 kg/m³)
- IS 456:2000, Table 9 — Nominal mix proportions and grade equivalents
Coefficients and the dry-volume factor on this page were last cross-checked against the sources above on 2026-07-11. Cement bag mass and density follow SLS 107; site units (cube = 100 ft³) follow standard Sri Lankan practice. Estimates are for material ordering — confirm structural mixes with your engineer.
Related tools
Comments & feedback
Spotted a bug or want an improvement? Tell us — our team reviews every comment, and good ideas get built. Comments are public and anonymous.
Found a bug, edge case, or want to suggest an improvement?
Email me at [email protected] — most fixes ship within 24 hours.