NBRO Landslide Clearance Fee Calculator (Sri Lanka)

NBRO clearance is compulsory before a local authority approves construction in ten Sri Lankan districts. Pick your district, land extent and building type, and this tool tells you whether you need it and what NBRO charges — straight from the department's own band tables, both of them.

By Induwara AshinsanaUpdated Sep 26, 2026
Do I need NBRO clearance, and what does it cost?
NBRO schedules · read 26 Sep 2026

Ten of the 25 districts are declared landslide prone.

NBRO prices housing by perch band, commercial by acre band.

The extent of the plot, not the floor area. 1 acre = 160 perches.

Concession
Try a case
NBRO clearance is required in Kandy

Kandy is one of the ten declared landslide-prone districts, so the local authority cannot approve the plan without an NBRO clearance certificate.

NBRO processing fee
Rs 750 – Rs 2,000
Two published figures — see the breakdown below.
Budget for the counter
Rs 2,025
Higher published fee Rs 2,000 + the Rs 25 form fee.

What each NBRO schedule charges

NBRO landslide-clearance page

undated · unchanged since at least 5 August 2022

Rs 750

  1. 16 perches falls in "Area is less than 20 Perches" (extent < 20 perches).
  2. Fee = Rs 750

NBRO Inspection Charges (LRAB)

Issue 01 · 1 Jan 2023, Revision 01 · 1 Feb 2023

Rs 2,000

  1. 16 perches falls in "Land area less than 20 Perches" (extent < 20 perches).
  2. Fee = Rs 2,000
  • NBRO publishes two different amounts for this band — Rs 750 on its landslide-clearance page and Rs 2,000 in its 2023 Inspection Charges document. Budget the higher figure and confirm at your NBRO district office.
  • The Rs 25 the local authority charges for the application form and guidelines is on top of this, and is paid to the council.

Both published tables, in full

House, religious or public building. Your row is highlighted.

Land extent, as NBRO prints itRule appliedClearance page2023 schedule
less than 20 Perchesyour plotextent < 20 perchesRs 750Rs 2,000
between 20 - 40 Perches20 ≤ extent ≤ 40 perchesRs 1,500Rs 2,500
between 40 - 60 Perches40 < extent ≤ 60 perchesRs 2,250Rs 3,000
between 60 - 80 Perches60 < extent ≤ 80 perchesRs 3,000Rs 3,500
between 80 - 100 Perches80 < extent ≤ 100 perchesRs 3,800Rs 4,000
between 100 Perches - 01 Acre100 < extent ≤ 160 perches (1 acre)Rs 4,500Rs 5,000
more than 01 Acreextent > 1 acreRs 6,000Rs 7,500
Low-income family or Samurdhi beneficiaryOverrides the bandRs 100not published

Extents above 1,000 acres are not priced here — NBRO quotes those in writing.

What to take with the application

Buildings use NBRO/01/LAB, the Landslide Risk Assessment for Building form. You buy it from the local authority or project-approving agency for Rs 25, and you hand the completed form back to that same office — not to NBRO directly. It must carry that office's official stamp.

  • Two copies of the survey plan prepared by a licensed surveyor, covering the plot and the surrounding area.
  • A copy of the deed.
  • A contour plan of the land at 1:1000 scale by a licensed surveyor — required only if NBRO has to perform a detailed investigation.
  • Construction drawings and the building layout plan, certified by a professionally qualified person, whenever a building is already proposed for the land.

Sources cited:both figures are transcribed from NBRO's own publications — the landslide-clearance page and the 2023 Inspection Charges document. Full citations and the methodology are below the calculator.

How it works

National Building Research Organisation clearance is a separate permission from your building permit, and the council will not issue the permit without it. The National Council for Disaster Management made NBRO's concurrence mandatory for construction in the areas it identifies as landslide prone, and NBRO instructs local authorities and project-approving agencies to require the certificate from their clients. The calculation has four steps, and no step estimates anything.

  1. Is clearance required at all? NBRO has declared ten districts landslide prone: Kandy, Matale, Nuwara Eliya, Badulla, Kegalle, Ratnapura, Kalutara, Galle, Matara, Hambantota. The test is the district, not the slope you can see from the road. In the other fifteen districts NBRO charges nothing because the clearance is not part of the approval. Inside Kalutara, Galle, Matara, Hambantota and the Mahiyangana, Embilipitiya, Dambulla, Galewela local-authority areas NBRO says exemptions may apply depending on the terrain — that is an inspection decision, so this tool never claims an exemption for an address.
  2. Which table, and which row? Housing, religious and public buildings are banded in perches; commercial, industrial and hotel land is banded in acres. Everything is normalised to perches internally at the statutory 1 acre = 160 perches, which is only used to read the band — land area conversion is a separate tool. The bands are published as “less than 20 Perches”, “between 20 - 40 Perches” and so on, which leaves the shared endpoints ambiguous. This tool reads the first row exactly as printed (strictly below its bound) and treats every later row as inclusive of its upper bound, so 20 perches and 40 perches both fall in the 20–40 row. Each row in the table above shows the inequality being applied, and a plot sitting exactly on a boundary should be confirmed at the district office.
  3. Concessions and formulas. A house built by a low-income family or a Samurdhi beneficiary is Rs 100 flat, and that row overrides the perch band entirely — the trap this tool exists to catch, because it is the single largest saving on the page. At the other end, commercial land above 5 acres leaves the table: the fee becomes the five-acre amount plus Rs 5,000 for each additional acre. NBRO does not say how a part-acre is treated, so a part-acre is rounded up to a whole additional acre here and the result says so.
  4. Two published figures, both shown.NBRO prices this fee twice. Its landslide-clearance page carries an undated table — Rs 750 for a house on under 20 perches. Its Construction Clearance page states the application processing fee by linking a controlled departmental document, “Inspection Charges” NBRO/LRRMD/IB/SH/IC, Issue 01 of 1 January 2023, Revision 01 of 1 February 2023, whose page 1 charges Rs 2,000 for the same band. The band structure is identical; every amount differs. The 2023 document is later and formally approved; the web page is what a reader lands on and is the only one carrying the Samurdhi row. Nothing in either says which supersedes the other, so this page shows both, recommends budgeting the higher, and points you at the district office. Interpolating between them would be inventing a number.

Two costs sit outside the NBRO fee. The local authority charges Rs 25 for the application form and the guidelines, paid to the council. And the building permit itself — application, planning, scrutiny and Certificate of Conformity — is a separate bill, which the building approval fee calculator estimates.

Both transcriptions are checked against an independent second implementation written directly from the printed rows, across every band edge and each side of it. 18/18 checks pass, including the worked examples below and a monotonicity test that a bigger plot never costs less.

Worked examples

16-perch family home, Gampola, Kandy district

  1. District: Kandy — one of the ten declared → clearance required
  2. Housing, no concession. 16 perches → the opening row (extent < 20 perches)
  3. Clearance page: Rs 750
  4. 2023 schedule: Rs 2,000
  5. Application form (paid to the council): Rs 25
  6. Budget: Rs 2,000 + Rs 25 = Rs 2,025

Samurdhi beneficiary's house on 25 perches, Ratnapura district — the concession case

  1. District: Ratnapura → clearance required
  2. 25 perches would fall in the 20–40 perch row (Rs 1,500 / Rs 2,500)
  3. But the low-income and Samurdhi row overrides the band entirely
  4. Clearance page: Rs 100
  5. 2023 schedule: Rs 2,500 — it publishes no concession row
  6. Take proof of Samurdhi entitlement; ask which schedule the counter is applying

7-acre industrial site, Kegalle district — the formula case

  1. District: Kegalle → clearance required
  2. Commercial. 7 acres is above the 5-acre top band, so the row is a formula
  3. Additional acres = ⌈7 − 5⌉ = 2
  4. Clearance page: Rs 38,000 + Rs 5,000 × 2 = Rs 48,000
  5. 2023 schedule: Rs 42,000 + Rs 5,000 × 2 = Rs 52,000
  6. Budget: Rs 52,000 + Rs 25 form = Rs 52,025

30-perch house, Gampaha district — the negative case

  1. District: Gampaha — not one of the ten declared districts
  2. NBRO clearance is not required, and NBRO charges nothing: Rs 0
  3. The local authority building permit fee is still payable
  4. If the council asks for NBRO clearance anyway, ask which declaration it relies on

NBRO fee for a house, by land extent

Housing, religious and public buildings in the ten declared districts, without the low-income concession. Both published figures shown.

Land extentClearance page2023 scheduleBudget
10 perchesRs 750Rs 2,000Rs 2,025
20 perchesRs 1,500Rs 2,500Rs 2,525
40 perchesRs 1,500Rs 2,500Rs 2,525
75 perchesRs 3,000Rs 3,500Rs 3,525
100 perchesRs 3,800Rs 4,000Rs 4,025
1 acre (160 perches)Rs 4,500Rs 5,000Rs 5,025
2 acresRs 6,000Rs 7,500Rs 7,525

A low-income or Samurdhi house is Rs 100 on the clearance page whatever the extent. Budget column adds the Rs 25 application form fee.

What this calculator does not price

  • NBRO/02/LAD — land development and subdivision. NBRO provides an estimate case by case.
  • NBRO/03/LAP — projects and construction other than buildings. NBRO provides an estimate case by case.
  • Any mitigation work NBRO makes a condition of the clearance. Retaining walls, drainage and slope stabilisation are a construction cost, quoted after inspection.
  • The local authority building permit. Use the building approval fee calculator for that bill.

Frequently asked questions

Sources & references

Every figure on this page was read from those NBRO publications on 2026-09-26. Note that www.nbro.gov.lk now redirects to nbri.gov.lk — the department has not moved, only its domain. The schedule changes only when NBRO reissues it, so this page is re-checked every six months and after any NBRO fee revision.

Related tools

Comments & feedback

Spotted a bug or want an improvement? Tell us — our team reviews every comment, and good ideas get built. Comments are public and anonymous.

Paid a different NBRO fee at the counter? That is the one thing I cannot check from here, and it would settle which schedule is live.

Email me at [email protected] — most fixes ship within 24 hours.